Extension: Portway Didcot |
Before extension |
Extension complete |
Extension complete |
|
Objective: Side Extension 4M X 10 M converting a 2 bed bungalow into a 4 double bed with on-suite bathroom. Also Creating a hallway with staircase leading to 2 of the bedrooms and bathroom. Method: Construction using conventional matching building materials according to the building regulations of 2006 (time of the build). All work and project managed by Chris Baker Builders. |
||||
Phase 1 - Sewage, domestic services, prepare footings, over site, and damp course level - 2 weeks |
|
![]() |
![]() |
|
Phase 2 - Complete up to plate height - 2 to 3 weeks |
![]() |
![]() |
![]() |
|
Phase 3 - Gable end brickwork, Felt batten tile and ridge the roof, sofits and fascia - 9 days |
![]() |
![]() |
![]() |
|
Phase 4 - First and Second fix electrical - 3 days. Plumbing - 3 days. Plastering - 3 weeks. Carpentry - 2 weeks |
![]() |
![]() |
![]() |
|
Phase 5 - Complete kitchen, dining room and finishing off - 3 to 4 days |
![]() |
|
||